Sunday 25 September 2016

Assignment #2 (Trains for NSEW Lines Safe For Service - Summary + Thesis + Reader Response) - First Draft

In the following news release, “Trains on the North-South and East West Lines Safe for Service”, Land Transport Authority (LTA) (2016) addressed the problems that it faced in regards to the North-South and East-West lines trains. It has also stated the actions taken to resolve the problems and how trains were subjected to tests to ensure their safeness and reliability. The webpage mentioned that complications were found on trains whereby the “battery housing” flew open due to pressure. Not only that, cracks were also found on the draughtscreen of 5 trains which were due to errors during installation. However, operation of train services were not affected as these problems were rectified immediately. LTA has also stated that hairline cracks were found on the “car-body shell” which was caused during production period. As it was impossible to repair the cracks, affected trains that were under warranty were sent back for replacement of parts at no costs. With a view to complete the rectification programme, LTA expressed that they would send two trains at a time for servicing. Nevertheless, this is dependent on the arrival of new trains along with the current ones which were still undergoing re-signalling. In order to ensure the safety and efficiency of the services, LTA has concluded that they will work closely with the contractors and SMRT. Based on the points elaborated, although LTA takes into consideration to ensure the safety and efficiency of the trains, they could have done better in handling this situation so as not to cause doubts and trust issues between commuters.

First of all, it may cause the public to have doubts and trust issues as based on LTA’s webpage, the news was released on Jul 2016. However, the train defects was found way back in 2013 but was not reported immediately. According to Kimberly (2016), she stated that: “Mr Khaw reiterated reasons why the issue was not made public earlier, saying that the hairline cracks on the trains did not pose any safety risk to commuters.”, since the hairline cracks did not pose any safety risks to commuters, LTA should have reported this matter to the public earlier. In Singapore, train breakdowns are increasing (Straits Times, 2016). With this being said, commuters are already losing faith in the train transport system. Withholding of such information in regards to the problems found on new trains, may increase the passengers’ distrust. If the situation was not major LTA should not have hidden this matter.

Secondly, it was mentioned that the hairline cracks did not pose any safety problems, however i feel that it does not fully justify why it still needs to be replaced. Based on FactWire (2016), a Hong Kong news agency contacted a retired Singaporean subway staff and quoted: “I’ve never encountered a situation like this in all my decades of working in railway construction. Replacing the whole frame [of the train] - you can tell how serious [the problem] is.”, through this statement, LTA should have given a more detailed report stating the reasons the trains are being sent back to China for replacement of body. Otherwise, it will cause the commuters to have doubts as LTA seems to be contradicting themselves.

Lastly, tighter quality checks for the components should have been done before installation. In my opinion, if these quality checks are done more thoroughly, it could have minimized the problems such as the explosion of the battery (GOV, 2016). According to The Independent (2016), FactWire interviewed former Hong Kong’s Kowloon-Canton Railway Corporation acting CEO and he agreed that the quality control standard was mediocre thus resulting in cracks and battery problems.

Although LTA did execute various actions to correct the problems, it was incomplete and they should have done more preventive than corrective actions.


(550 Words)


References

FactWire. (2016). China manufacturer for MTR secretly recalls 35 SMRT subway train after cracks found. Retrieved, September 24, 2016 from https://www.factwire.news/en/MTR-securetly-recall.html

Tan, C. (2016) Cracks on MRT trains: Khaw addresses key issues raised. The Straits Times. Retrieved, September 25, 2016 from http://www.straitstimes.com/singapore/transport/rise-in-major-breakdowns-but-mrt-gets-more-reliable-lta

Spykerman, K. (2016). Lessons to be learnt from defective SMRT trains incident: Khaw.   Retrieved from http://www.channelnewsasia.com/news/singapore/lessons-to-be-learnt-from/3048928.html

LTA says train defects “not safety-critical” but ex-HK CEO says QC of entire manufacturing process under suspicion. The Independent (2016).  Retrieved, September 24, 2016 from http://theindependent.sg/lta-says-train-defects-not-safety-critical-but-ex-hk-ceo-says-qc-of-entire-manufacturing-process-under-suspicion/

Trains on the North-South and East West Lines Safe for Service. (2016). Land Transport Authority. Retrieved, September 20, 2016, from https://www.lta.gov.sg/apps/news/page.aspx?c=2&id=0f8b1220-0289-4bef-99c9-b2455f17a66c#_ftn1

Why are MRT trains being shipped back to manufacturer?. Gov. (2016). Retrieved, September 25, 2016 from https://www.gov.sg/factually/content/why-are-mrt-trains-being-shipped-back-to-its-manufacturer


No comments:

Post a Comment