In the following news release,
“Trains on the North-South and East West Lines Safe for Service”, Land
Transport Authority (LTA) (2016) addressed the problems that it faced in
regards to the
North-South and East-West lines trains. It has also stated the actions taken to
resolve the problems and how trains were subjected to tests to assure the
public on their safeness and reliability. The webpage also mentioned the
problems that were found on trains. These include “battery housing” flew open
due to pressure, however it was rectified immediately by the manufacturer. Other
than that, cracks on 5 of the trains’ draughtscreens due to installation errors
and hairline cracks on “car-body shell” were also found. Nonetheless, operation
of train services were not affected as these trains were tested to be safe for
use. As it was impossible to repair the hairline cracks, affected trains that
were under warranty were returned back for replacement of components. With a
view to complete the rectification programme, LTA expressed that they would
sent back trains in pair at a time for servicing. Nevertheless, this is
dependent on the arrival of new trains along with the current ones which were
still undergoing re-signalling so as to ensure there are sufficient trains for
running. In order to ensure the safety and efficiency of the services, LTA has
concluded that they will work closely with the contractors and SMRT. Based on the points elaborated,
although LTA takes into consideration to ensure the safety and efficiency of
the trains, they could have done better in handling this situation so as not to
cause doubts and trust issues between commuters.
First of all, it may cause the
public to have doubts and trust issues as based on LTA’s webpage, the news was
released on Jul 2016. However, the train defects was found way back in 2013 but
was not reported immediately. According to Kimberly (2016), she stated that: “Mr Khaw
reiterated reasons why the issue was not made public earlier, saying
that the hairline cracks on the trains did not pose any safety risk to
commuters.”, since the hairline cracks did not pose any safety risks to
commuters, LTA should have reported this matter to the public earlier. In
Singapore, train breakdowns are increasing (Straits Times, 2016). With this
being said, commuters are already losing faith in the train transport system. In
my opinion, withholding of such information in regards to the problems found on
new trains, may increase the passengers’ distrust. If the situation was not
major LTA should not have hidden this matter.
Secondly, it was mentioned that the hairline cracks did not
pose any safety problems, however I feel that it does not fully justify why it
still needs to be replaced. Based on FactWire (2016), a Hong Kong news agency
contacted a retired Singaporean subway staff and quoted: “I’ve never encountered a situation like
this in all my decades of working in railway construction. Replacing the whole
frame [of the train] - you can tell how serious [the problem] is.”, through
this statement, LTA should
have given a more detailed report stating the reasons the trains were being
sent back to China for replacement of body. Otherwise, it will cause the
commuters to have doubts as LTA seems to be contradicting themselves. Stating
that the hairline cracks did not pose any safety problems yet it needs to be
replaced.
Lastly, tighter
quality checks for the components should have been done before installation. In
my opinion, if these quality checks are done more thoroughly, it could have
minimized the problems such as the explosion of the battery (GOV, 2016). As they
could have removed the battery with defects before even installing it and
situation like this would not had happened. According to The Independent
(2016), FactWire
interviewed former Hong Kong’s Kowloon-Canton Railway Corporation acting CEO
and he agreed that the quality control standard was mediocre thus resulting in
cracks and battery problems.
Although LTA did execute various actions to correct the
problems, it was incomplete and they should have done more preventive than
corrective actions.
(600 Words)
References
FactWire. (2016). China
manufacturer for MTR secretly recalls 35 SMRT subway train after cracks found. Retrieved,
September 24, 2016 from https://www.factwire.news/en/MTR-securetly-recall.html
LTA says train defects “not
safety-critical” but ex-HK CEO says QC of entire manufacturing process under
suspicion. The Independent (2016). Retrieved, September 24,
2016 from http://theindependent.sg/lta-says-train-defects-not-safety-critical-but-ex-hk-ceo-says-qc-of-entire-manufacturing-process-under-suspicion/
Spykerman, K. (2016). Lessons to be learnt from defective
SMRT trains incident: Khaw. Retrieved
from http://www.channelnewsasia.com/news/singapore/lessons-to-be-learnt-from/3048928.html
Tan, C. (2016) Cracks on
MRT trains: Khaw addresses key issues raised. The Straits Times. Retrieved,
September 25, 2016 from http://www.straitstimes.com/singapore/transport/rise-in-major-breakdowns-but-mrt-gets-more-reliable-lta
Trains on the North-South and
East West Lines Safe for Service. (2016). Land Transport Authority. Retrieved,
September 20, 2016, from https://www.lta.gov.sg/apps/news/page.aspx?c=2&id=0f8b1220-0289-4bef-99c9-b2455f17a66c#_ftn1
Why are MRT trains being shipped
back to manufacturer?. Gov. (2016). Retrieved, September 25, 2016
from https://www.gov.sg/factually/content/why-are-mrt-trains-being-shipped-back-to-its-manufacturer